Ashington No.5 Update

A short update on recent work which has taken place on Ashington No.5's overhaul over the past few weeks,

Following on from the last post which saw George chop the ends of the new crosshead slippers off, all the new slippers have now been milled and filed back to the right length

The last two jobs on the slippers for George were to cut the oil ways and drill and tap the four holes which take the bolts to fit the slipper to the crosshead

Michael plasma cutting the new axle box face wear plates to size

Three of the six wear plates cut out, cleaned up around the edges and ready for welding

Chris begins welding the first wear plate to the axle box




Two down, four to go

The following day, Michael and Alan trial fit one of the axleboxes which has had its wear plate welded on


A good fit

Tom making a start re-fitting the horn guides

Tom and Alan discussing the work before fitting more horn guide bolts

Tom turning more bolts in the lathe

George setting up the dividing head on the mill...

...to machine bolt heads for the newly turned horn guide bolts