Wednesday, 20 March 2024

Ground Frame Installation

Michael, James, Richard, Thomas and Aaran have been grafting today with the next step in the redevelopment of Middle Engine Lane yard - the installation of two ground frames.


The new position of the first ground frame, which will be used to control the points at both ends of the new crossover between the mainline and the south headshunt.


James and Michael discussing installing point rodding...


...which Thomas is progressing.


Working installing the locking mechanism.

No comments: