Richard and Michael cutting a section of ACC5's new ashpan down to size whilst Robert and Aaran remove the blanking plates fitted to the regulator to enable the hydraulic exam to be carried out.


Robert fitting and splitting split pins in the brake rigging.


Richard welding the ashpan together.


Later, Joe and Aaran used 08915 to shunt the pit road.


The Sentinel being shunted to the bottom of the workshop so ACC5 can be stabled over the pit to allow the ashpan to be finished.