Work has continued on digging the hole outside the museum 'new road' which was started at the back end of August. Following on from the last post volunteers have acquired the use of a mini digger to continue the work |
The digger makes short work of the remaining concrete and then loads up the dumper |
The ballast in the four-foot is spread out evenly into the other two sections |
Compacting it down flat so there is a better layer for the concrete to be laid onto |
Digging further out |
The sleepers and what was left of the remaining concrete after being dugout. The ground was then levelled and marked out ready for cement |