| With the rollers firebox now on its other side, Tom continues burning out the foundation ring rivets. Another step forward to getting the inner firebox out |
Showing posts with label Road Steam. Show all posts
Showing posts with label Road Steam. Show all posts
Monday, 3 May 2021
Work on the rollers firebox
Tuesday, 23 March 2021
More work on the steam rollers boiler
Friday, 19 March 2021
Work on the steam rollers boiler
Friday, 26 February 2021
Work on the roller
Monday, 1 February 2021
Loading the lowmac
Saturday, 16 January 2021
Friday, 6 November 2020
Work on the steam roller
Friday, 9 October 2020
Rivet work on the roller
Pictures and a couple videos of Adam, from Northern Steam Engineering Ltd, burning out rivets on the steam rollers boiler barrel/firebox lap
Tuesday, 8 September 2020
Rivet removal
Friday, 4 September 2020
Work on the roller
Tuesday, 11 August 2020
Friday, 26 June 2020
Removing the rollers rolls
Yesterday, volunteers Tom, Steve, Richard and Michael spent the day removing the front and back rolls as well as the headstock off the roller
| The 'before' shot |
| The front of the barrel was jacked and packed to lift the headstock clear of the pivot pin, once it was cleared we carefully dragged it out using the tractor and packed it on the hardstand |
| Front roll off |
| For the back rolls we jacked and packed under the foundation ring to lift the rolls off the ground. Then, using the a-frame, we pulled the rolls from the axle and dragged them back clear |
| Headstock removed after a bit of a battle with the nuts and bolts |
Friday, 19 June 2020
Roller update
| Some photos from last week of work on the roller, here Tom is cleaning up the crosshead prior to shotblasting |
| Showing where the cross head has come from after splitting it from the piston rod, since this photo has been taken the piston rod and piston have also been removed |
| Safety valve cover face receiving a clean up before fitting a blanking plate |
| The 2-ton a-frame was used to remove the tender |
Tuesday, 9 June 2020
Work on the steam roller
Monday, 8 June 2020
Steam Roller
A few weeks ago we took delivery of a steam roller which is privately owned by one of our volunteers
![]() |
| Ready to be loaded up at its old home |
![]() |
| Arriving at the railway |
![]() |
| After being successfully unloaded the tractor was used to shunt the roller about |
![]() |
| Work began a few days after arrival with the removal of the boiler tubes |
![]() |
| On the hardstand for washout |
![]() |
| Motion dismantled |
![]() |
| More progress to follow soon |